Bill Sponsor
House Bill 2122
115th Congress(2017-2018)
To reinstate and extend the deadline for commencement of construction of a hydroelectric project involving Jennings Randolph Dam.
Became Law
Became Law
Became Public Law 115-205 on Jul 23, 2018
Overview
Text
No Linkage Found
About Linkage
Multiple bills can contain the same text. This could be an identical bill in the opposite chamber or a smaller bill with a section embedded in a larger bill.
Bill Sponsor regularly scans bill texts to find sections that are contained in other bill texts. When a matching section is found, the bills containing that section can be viewed by clicking "View Bills" within the bill text section.
Bill Sponsor is currently only finding exact word-for-word section matches. In a future release, partial matches will be included.
No Linkage Found
About Linkage
Multiple bills can contain the same text. This could be an identical bill in the opposite chamber or a smaller bill with a section embedded in a larger bill.
Bill Sponsor regularly scans bill texts to find sections that are contained in other bill texts. When a matching section is found, the bills containing that section can be viewed by clicking "View Bills" within the bill text section.
Bill Sponsor is currently only finding exact word-for-word section matches. In a future release, partial matches will be included.
H. R. 2122 (Enrolled-Bill)
H. R. 2122


One Hundred Fifteenth Congress of theUnited States of America

AT THE SECOND SESSION

Begun and held at the City of Washington on Wednesday,
the third day of January, two thousand and eighteen

an act

    To reinstate and extend the deadline for commencement of construction of a hydroelectric project involving Jennings Randolph Dam.

Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled,

SECTION 1. Reinstatement and extension of time for a Federal Energy Regulatory Commission Project involving Jennings Randolph Dam.

(a) Extension of time.—Notwithstanding the time period specified in section 13 of the Federal Power Act (16 U.S.C. 806) that would otherwise apply to the Federal Energy Regulatory Commission project numbered 12715 (referred to in this section as the “project”), the Federal Energy Regulatory Commission (referred to in this section as the “Commission”) may, at the request of the licensee for the project, and after reasonable notice, in accordance with the good faith, due diligence, and public interest requirements of, and the procedures of the Commission under, that section, extend the time period during which the licensee is required to commence the construction of the project for not more than 3 consecutive 2-year periods that begin on the date of the expiration of the extension originally issued by the Commission.

(b) Obligation of licensee.—Any obligation of the licensee for the project for the payment of annual charges under section 10(e) of the Federal Power Act (16 U.S.C. 803(e)) shall commence on the expiration of the time period to commence construction of the project, as extended by the Commission under subsection (a).

(c) Reinstatement of expired license.—

(1) IN GENERAL.—If the period required for the commencement of construction of the project has expired before the date of enactment of this Act, the Commission may reinstate the license effective as of the date of the expiration of the license.

(2) EXTENSION.—If the Commission reinstates the license under paragraph (1), the first extension authorized under subsection (a) shall take effect on the date of the expiration of the license.

Attest:





Speaker of the House of Representatives.  

Attest:





Vice President of the United States and   